EDC allots P3 billion to upgrade Negros geothermal plant

Brix Lelis - The Philippine Star

MANILA, Philippines — Lopez-led Energy Development Corp. (EDC) is investing around P3 billion to expand the generating capacity of its existing geothermal plant in Negros Oriental.

EDC, through Green Core Geothermal Inc. (GCGI), has sought environmental clearance to upgrade the turbine system of its 112.5-megawatt (MW) Palinpinon 1 Geothermal Power Plant Project.

In a filing to the Department of Environment and Natural Resources (DENR), GCGI said the three 37.5-MW turbine generators would be replaced with 42-MW units to expand the facility’s total capacity to 126 MW.

“This upgrade is prompted by the fact that two of the turbine rotors are approaching the end of their asset life within two to three years,” the company said.

GCGI said the expansion would not require additional land, changes in process technology or higher steam usage.

Despite the planned capacity increase, the firm said emissions would remain unchanged as the enhanced efficiency of the new turbines offsets the additional output.

The investment for this project covers the expenses incurred from project planning, engagement activities with consultants, due diligence, procurement of turbine systems and installation.

For the plant’s proposed upgrade, the DENR’s Environmental Management Bureau is set to conduct a public scoping activity on July 23 in Negros Oriental, inviting interested and concerned parties.

The public scoping is an early stage in the environmental impact assessment process where the proponent presents an overview of the project and other relevant information to provide the scope of work and terms of reference.

Initially built by National Power Corp., the Palinpinon 1 project is one of the geothermal power plants operated by GCGI in Negros Oriental.

The facility has been delivering clean power to the national grid since 1983.

A subsidiary of First Gen Corp., EDC currently owns and operates 13 geothermal plants totaling about 1,200 MW. This is equivalent to roughly 60 percent of the country’s geothermal capacity.

DENR

EDC

  • Latest
  • Trending
Latest
Latest
abtest
Recommended
Are you sure you want to log out?
X
Login

Philstar.com is one of the most vibrant, opinionated, discerning communities of readers on cyberspace. With your meaningful insights, help shape the stories that can shape the country. Sign up now!

Get Updated:

Signup for the News Round now

FORGOT PASSWORD?
SIGN IN
or sign in with