Aboitiz Renewables unit plans P512M facility for solar link

From AB Capital's The Opening Bell: Three Moves
Event
AP filed with ERC to build a P512mn dedicated transmission line linking its 239.56MWdc Luna Solar Power Project + 65MW BESS in Cadiz, Negros Occidental, to the Visayas grid. Construction starts this quarter, with COD targeted 4Q2027, connecting to the 230kV Cadiz Substation (~5km away).
View
Dedicated transmission ensures timely commissioning, full dispatch, and revenue recognition for Luna, reducing operational and opportunity-cost risk. The project will support cash flows and earnings, but is not expected to materially impact AP’s results until 2028.
Catalyst
Key near-term triggers include ERC approval, EPC finalization, construction progress, and grid interconnection testing. Upside comes from on-time completion and lower-than-expected capex; risks include permitting delays, cost overruns, or interconnection constraints.
Action
We maintain Outperform on AP with a TP of P54/sh. The development will only be earnings-accretive in 2028, but investors can monitor project milestones for selective accumulation, as successful transmission completion unlocks long-term renewable cash-flow visibility.
Disclaimer: The information, analyses, and views contained herein is based on sources which we, AB Capital Securities, believe are reliable, but is not guaranteed by us and is not to be considered all inclusive. It is not to be construed as an offer or solicitation of an offer to sell or buy the securities herein mentioned. AB Capital Securities and its Directors and Officers and/or members of their families may have a position in the securities herein mentioned and may make purchases and/or sales of the securities from time to time in the open-market and otherwise.