MANILA, Philippines — President Ferdinand Marcos Jr. on Friday, September 5, said that the government takeover of the Siquijor Island Power Corp. (SIPCOR) was necessary as the service showed no improvement.
The Energy Regulatory Commission ordered a shutdown of the Villar-owned SIPCOR after it violated multiple operational and regulatory requirements.
“We had to take over the operations of SIPCOR for the simple reason that wala tayong nakikitang improvement doon sa kanilang pag-provide ng supply ng kuryente kaya’t ganoon ang nangyari,” Marcos said.
(We had to take over the operations of SIPCOR for the simple reason that we did not see an improvement in their electricity supply so that’s what happened.)
The Province of Siquijor Electric Cooperative (PROSIELCO) will be the one to supply power to the island, alongside the ERC and the National Electrification Administration (NEA).
Marcos himself led the ceremonial switch-on of the 17.8-megawatt power plant on Friday morning, September 5. He had previously visited the island on June 11 to assess its longstanding issues of power outages.
The new power plant is projected to supply 17 megawatts of power, exceeding the island's requirement of nine megawatts.
The president proudly proclaimed that the island’s power supply has been completed.
Siquijor has long had issues with power supply, with Marcos addressing the problem in his fourth State of the Nation Address.
Marcos said that when he inspected the island’s power facilities, the permits had expired and the generators were broken. He then told the Department of Energy, NEA and ERC to make sure that services returned to normal.