Governor wants BOI to force JG Summit to locate its petrochem project in Bataan
March 28, 2005 | 12:00am
Former Congressman and now Governor of Bataan Enrique Garcia is opposing the recent decision of the Board of Investments (BOI) to approve the planned location of JG Summit Petrochemical Corp.s (JGSPC) naphtha cracker plant in Batangas.
Garcia said that the first proposed naphtha cracker project, by then proponent, Luzon Petrochemical Corp. (LPC), was supposed to be built in Bataan.
The BOI had approved the project and gave the necessary incentives way back in 1988.
However, LPC took on Shell as a partner and it was decided to relocate the project to Batangas to combine the facility with Shells liquefied petroleum gas facility.
Garcia, through a series of lawsuits, was able to get a ruling from the Supreme Court in 1990 that an investor does not have the final say on where he wants to locate his investment.
However, the planned LPC/Shell naphtha cracker project was eventually shelved.
But based on that SC ruling, Garcia wants the BOI to force JGSPC to locate its project in Bataan.
Initially, Garcia plans to use non-legal means to convince the BOI and JGSPC to locate the planned naphtha cracker project to Bataan.
However, if the BOI and JGSPC ignores his argument, Garcia is ready to take legal action to force the BOI and JGSPC to adhere to the SC ruling covering the then LPC/Shell naphtha cracker project.
The BOI had recently approved JGSPCs application for registration on a pioneer basis as a new domestic producer of ethylene, propylene, pyrolysis gas and other by-products.
Based on its application documents with the BOI, the JGSPC naphtha cracker project would have a cost of P26.247 billion to be financed primarily from loans amounting to P18.373 billion and equity contribution of P7.874 billion.
The JGSPC naphtha cracker project, however, is scheduled to start commercial operation by December 2008.
The projected output of JGSPC is 318 metric tons of ethylene, 189 MT of propylene, 218 MT of py gas, 150 MT of fuel gas (for JGSPCs own use) and 28 MT of fuel oil (of which 16 MT or 58 percent would be for JGSPCs own use and 12 MT or 42 percent for sale).
JGSPCs major stockholder is JG Summit Holdings Inc. with 82.28 percent, followed by Marubeni Corp.with 17.71 percent.
Garcia said that the first proposed naphtha cracker project, by then proponent, Luzon Petrochemical Corp. (LPC), was supposed to be built in Bataan.
The BOI had approved the project and gave the necessary incentives way back in 1988.
However, LPC took on Shell as a partner and it was decided to relocate the project to Batangas to combine the facility with Shells liquefied petroleum gas facility.
Garcia, through a series of lawsuits, was able to get a ruling from the Supreme Court in 1990 that an investor does not have the final say on where he wants to locate his investment.
However, the planned LPC/Shell naphtha cracker project was eventually shelved.
But based on that SC ruling, Garcia wants the BOI to force JGSPC to locate its project in Bataan.
Initially, Garcia plans to use non-legal means to convince the BOI and JGSPC to locate the planned naphtha cracker project to Bataan.
However, if the BOI and JGSPC ignores his argument, Garcia is ready to take legal action to force the BOI and JGSPC to adhere to the SC ruling covering the then LPC/Shell naphtha cracker project.
The BOI had recently approved JGSPCs application for registration on a pioneer basis as a new domestic producer of ethylene, propylene, pyrolysis gas and other by-products.
Based on its application documents with the BOI, the JGSPC naphtha cracker project would have a cost of P26.247 billion to be financed primarily from loans amounting to P18.373 billion and equity contribution of P7.874 billion.
The JGSPC naphtha cracker project, however, is scheduled to start commercial operation by December 2008.
The projected output of JGSPC is 318 metric tons of ethylene, 189 MT of propylene, 218 MT of py gas, 150 MT of fuel gas (for JGSPCs own use) and 28 MT of fuel oil (of which 16 MT or 58 percent would be for JGSPCs own use and 12 MT or 42 percent for sale).
JGSPCs major stockholder is JG Summit Holdings Inc. with 82.28 percent, followed by Marubeni Corp.with 17.71 percent.
BrandSpace Articles
<
>
- Latest
- Trending
Trending
Latest