Cebu News

P3.8 billion spent for anti-flood

Iris Hazel Mascardo - The Freeman

CEBU, Philippines — For three years, since 2022, the Department of Public Works and Highways (DPWH) has outlined a total of 104 flood control projects in Cebu City, which have already amounted to P3.8 billion, but the city government noted that only 70 of these projects were completed.

Cebu City Mayor Nestor Archival expressed his frustrations with the projects under the DPWH, including flood controls, which he assessed to be either delayed or causing inconvenience to the public.

Archival then spearheaded a meeting with various city contractors under the DPWH. For him, this marked the breaking point of his frustration over the growing number of public complaints on the delayed infrastructure projects in the city, many of which remain incomplete.

In line with this, the DPWH–Cebu City District Engineering Office, under the leadership of District Engineer Manolo Madronio Jr., released the list of flood control projects, noting a timeline from 2022 to 2025.

As a rundown, the city has listed a total of 104 flood control projects under the DPWH from 2022 to 2025, totaling P3.8 billion. Of this number, 70 have been completed, 22 are ongoing, four were suspended, and eight have yet to commence.

The data also indicated that among the projects completed are flood mitigation structures along Butuanon River, Lahug River, Guadalupe River, Kinalumsan River, and Mananga River.

It also reflects multiple drainage system constructions in various barangays such as Capitol Site, Cogon Ramos, Day-as, Kalubihan, Luz, Pulangbato, Sambag I, San Antonio, San Roque, T. Padilla, Tinago, Camputhaw, Lorega, Pari-an, and Sto. Niño.

Just weeks ago, the Cebu City Council called upon the Cebu City Planning and Development Office (CPDO) and the DPWH to update the council on the status of the city's drainage master plan within 15 days, after pointing out that widespread flooding stems from the city's outdated drainage systems.

While it has been openly broadcast that Cebu City’s drainage system is already outdated—thus primarily contributing to the perennial flooding in the city—it has been revealed that the biggest hurdle to its upgrade is actually the acquisition of lots. This was also according to Councilor David Tumulak during previous interviews.

As of the present, 22 projects are ongoing and are mostly for constructing flood mitigation structures and drainage systems in other areas.

These include Barangay Basak San Nicolas; along Lahug River in Barangay T. Padilla; along Mananga River in Barangays Bonbon and Buot-Taup; along Guadalupe River in Barangay Kalunasan; along Kinalumsan River; and along Bulacao River.

There is also ongoing construction of drainage structures along Salinas Drive and Gorordo Ave., as well as in Barangays Talamban, Mabolo, Pit-os, and Poblacion Pardo.

The data from the DPWH also indicated that there were suspended flood mitigation structures in Barangay Talamban; construction of Flood Mitigation Structure, Package 2, at A. Gabuya St. to Outfall; construction of Flood Mitigation Structure along Guadalupe River, Package 2, Barangay Sapangdaku; and construction of Revetment along Lusaran River, Barangay Tagbao.

The same data, however, did not indicate the reason for the suspension.

Meanwhile, flood mitigation structures in Cotcot River, Barangay Day-as, and various barangays like Sta. Cruz, Agsungot, Carreta, Sambag I, Ermita, Sto. Niño, and T. Padilla are yet to commence.

It was also noted that the flood mitigation project with the highest cost is the construction of a structure along Butuanon River, Brgy. Pulangbato, undertaken by On Point / UKC, with a cost of P96,500,000.

At least eleven projects were awarded to BNR Construction, including joint ventures with other firms.

Belconstruct, Helm Construction, and AST had five projects each, while WTG Construction, Planac Construction, Gowil Builder, and Kyle Construction Services were awarded four each.

Five days ago, amid delays in multiple infrastructure projects—not just flood control projects—Archival couldn’t help but flare up against the DPWH and its contractors, reiterating the demand for a five percent penalty fine.

In light of the delays, Archival gave specific ultimatums for each project, which will be outlined in the Commitment of Undertaking. While fast-tracking is the goal, Archival stressed that the quality of the projects must not be compromised.

As for contractors who failed to attend the meeting, Archival said their absence has been noted and that the city is considering blacklisting them from future city-funded projects.

Among Archival’s proposals is the imposition of a five percent penalty based on ten percent of the overall project cost. To avoid legal technicalities, he said that the commitment must come from the contractors themselves and be formalized through the Commitment of Undertaking. (CEBU NEWS)

DPWH

  • Latest
Latest
Latest
abtest
Recommended
Are you sure you want to log out?
X
Login

Philstar.com is one of the most vibrant, opinionated, discerning communities of readers on cyberspace. With your meaningful insights, help shape the stories that can shape the country. Sign up now!

Get Updated:

Signup for the News Round now

FORGOT PASSWORD?
SIGN IN
or sign in with