Metro Manila flood project completion extended for 6 months

MANILA, Philippines — The Economy and Development Council, chaired by President Marcos, has approved a six-month extension of the Metro Manila Flood Management Project (MMFMP)’s Phase 1.
The completion of the seven remaining pumping stations under the MMFMP Phase 1 was among the key issues discussed during the 12th meeting of the council at Malacañang.
The project’s deadline will be moved from Dec. 2, 2026 to May 31, 2027, without changing its approved scope or total project cost, the Presidential Communications Office (PCO) said.
“The extension will give the Department of Public Works and Highways and Metropolitan Manila Development Authority enough time to complete the remaining construction works, testing, acceptance and turnover of the facilities,” the PCO said.
The seven pumping stations are part of the project’s original target of 38 facilities across Metro Manila.
“Once completed and fully operational, these facilities are expected to improve floodwater management capacity and protect communities in flood-prone areas,” the PCO said.
“The proposed extension will be the project’s second and final extension, with the remaining period dedicated to completing the facilities and ensuring these are ready for operation,” the PCO added.