MCC-funded road project in Samar on track

The Philippine Star

MANILA, Philippines - The Millennium Challenge Account-Philippines (MCA-P) has reported progress in all of the contract packages which make up the $214.4-million Secondary National Roads Development Project (SNRDP) funded by the Millennium Challenge Corp. (MCC).

The 222-kilometer SNRDP is composed of four contract packages that begin in the Pan Philippine Highway/Buray (Wright) in Samar and end in Guiuan, Eastern Samar.

In a recent media briefing in Borongan, Samar, MCA-P managing director and chief executive officer Marivic Anounuevo said all contract packages are in full swing.

As of end-July, contract package (CP) 1 that covers 16.36-km road from Barangay Buray to Barangay Tinani in Paranas, Samar registered a completion rate of 52.06 percent, ahead of the projected rate of 37.69 percent. With the current pace, it is expected to be completed before the end of the year, way ahead of the April 14, 2014 schedule.

CP3, which runs from San Julian to Balangkayan in Eastern Samar, posted 14.57 percent progress, slightly higher than the 14.14 percent target. Road clearing in CP4, meanwhile, is being fast-tracked. The P2.2-billion contract covers 77.51-km road from Llorente to Guiuan.

The P2.5-billion CP2, awarded only last June, is the largest in terms of value.

BARANGAY BURAY

BARANGAY TINANI

EASTERN SAMAR

GUIUAN

MARIVIC ANOUNUEVO

MILLENNIUM CHALLENGE ACCOUNT-PHILIPPINES

MILLENNIUM CHALLENGE CORP

PAN PHILIPPINE HIGHWAY

SAMAR

SAN JULIAN

SECONDARY NATIONAL ROADS DEVELOPMENT PROJECT

  • Latest
  • Trending
Latest
Latest
abtest
Are you sure you want to log out?
X
Login

Philstar.com is one of the most vibrant, opinionated, discerning communities of readers on cyberspace. With your meaningful insights, help shape the stories that can shape the country. Sign up now!

Get Updated:

Signup for the News Round now

FORGOT PASSWORD?
SIGN IN
or sign in with