Only 1 of 16 operational - COA: P2.5B water projects idle

Jonnavie Villa - The Freeman

CEBU, Philippines — Only one of Cebu Province’s 16 bulk water supply projects funded through its 20-percent Development Fund from 2021 to 2025 has become fully operational, despite ?879.32 million in payments, according to the Commission on Audit (COA).

In its 2025 annual audit report, COA flagged delays and implementation problems affecting the projects, which had a combined contract cost of ?2.556 billion.

The audit found that 15 projects remained non-operational, with some physically completed but idle, others still under construction, suspended or terminated.

COA said the prolonged non-operation of the facilities reflected deficiencies in project planning and implementation, resulting in the non-utilization of infrastructure intended to provide communities with water services.

Only the Moalboal Bulk Water Supply Project was fully operational.

Among the completed but idle facilities were the Alcoy Bulk Water Supply Project, costing ?21.60 million; Santander Bulk Water Supply Cluster A, worth ?15.84 million; and Barili Bulk Water Supply Cluster B, amounting to ?26.75 million.

COA noted that the Alcoy and Santander facilities remained unused because their water sources depended on other projects that encountered problems.

The Santander project, completed on Dec. 31, 2023, could not operate because its water source depended on the Samboan Bulk Water Supply Project, whose contract was terminated on Sept. 16, 2025.

Alcoy’s water source, meanwhile, depended on the Boljoon project, which was also terminated.

For Barili Cluster B, the Provincial Engineering Office (PEO) encountered difficulties securing a permit from the National Water Resources Board because of issues involving the usufruct agreement for the site of its water treatment facility.

Four other projects, with combined payments of ?378.93 million, remained under construction. These covered the completion of Barili Bulk Water Supply Clusters A and C, the Moalboal project, Oslob Cluster A and the Tabogon Bulk Water Supply Project.

Three projects in Dalaguete, Malabuyoc and San Fernando, with payments totaling ?147.20 million, were suspended.

Another five contracts, worth a combined ?232.09 million, were terminated. These covered Argao Cluster A, Boljoon Cluster A, Barili Clusters A and C, Alegria and Samboan Cluster A.

COA attributed the terminations to negative slippage, inflationary pressures and contractor-related problems.

In Argao, auditors found unfinished water-source structures and a partially constructed concrete tank. Pipeline installation in some barangays had also been abandoned following the contract termination, leaving the installed infrastructure unusable.

The Boljoon project likewise had partially installed water tanks and pipelines, while two major tanks and the treatment facility remained unfinished.

COA also observed rusting metal reinforcements and unfinished structures exposed to environmental elements.

In Alegria, water tanks had been installed, but the treatment facility remained incomplete and distribution pipelines were still unburied. The project was only 18.59 percent complete and faced possible termination following the revocation of the contractor’s license.

Asked about the delays, Engr. Aldrin Barade, head of the Cebu Provincial Inter-LGU Waterworks Systems Office (CPIWSO), cited contractor-related implementation problems, land acquisition and right-of-way issues.

"Usually is sa implementation, sa contractor nga side, 'no? Naa jud silay delays," Barade said.

He also cited difficulties acquiring land and securing right-of-way for pipeline installation.

Barade clarified that the PEO supervises project construction, while completed facilities are turned over to the concerned office for operation or other arrangements.

He said some projects were also suspended pending legal review, although he could not immediately identify which ones were covered.

On terminated contracts, Barade said the provincial government was assessing how to use the remaining infrastructure and completed works to prevent the investments from going to waste.

"Gi-review pa na sila kay sayang man gud ang mga assets, especially accomplishment," he said.

He added that the province was considering redesigning or rebidding the affected projects, depending on the results of technical and legal assessments.

"So possibly, sa amo nga side is we want to make use of that assets. So basin naay redesign or rebidding nga magamit na sila," Barade said.

COA recommended that provincial management, through the PEO and Provincial Planning and Development Office, assess the technical, financial and operational status of all bulk water supply projects funded through the 20-percent Development Fund from 2021 to 2025.

It also urged the province to adopt a time-bound strategy to address implementation problems and put viable projects into operation, particularly those already completed or nearing completion.

The audit agency further called for regular inspections and protective measures for unfinished or idle facilities to prevent deterioration and further losses in public funds.

COA stressed that technical, contractual and regulatory issues must be addressed to ensure the projects deliver their intended benefits to the communities they are meant to serve. — (FREEMAN)

TRENDING

  • Latest
Latest
Latest
abtest
Recommended
Are you sure you want to log out?
X
Login

Philstar.com is one of the most vibrant, opinionated, discerning communities of readers on cyberspace. With your meaningful insights, help shape the stories that can shape the country. Sign up now!

Get Updated:

Signup for the News Round now

FORGOT PASSWORD?
SIGN IN
or sign in with