CEBU, Philippines — The Cebu provincial government is targeting the opening of its long-unused sports complex in Lahug, Cebu City, in the first quarter of 2027, following years of inactivity and deterioration flagged by state auditors.

Governor Pamela Baricuatro announced the timeline during a press conference on Wednesday, November 25, saying the provincial government had already addressed the concerns surrounding the facility.

She said the sports complex would soon be available for public use, including recreational activities such as pickleball.

“Magamit na siya. Pwede namo mag-pickleball didto,” the governor added.

The planned opening comes after the Commission on Audit (COA), in its 2025 audit report, raised concerns over the facility's prolonged non-utilization despite being reported completed more than five years ago.

P21.8 Million complex left unused

The Cebu Provincial Sports Complex, located on a province-owned property in Sitio Sudlon, Barangay Lahug, Cebu City, was constructed at a revised cost of P21,839,370.75.

The project was undertaken and dated September 13, 2018, with an initial contract price of P19.96 million charged against the province's 20-percent development fund.

The project cost later increased through a variation order, bringing the total to P21.8 million, while its implementation period was extended.

Former governor Hilario Davide III led the groundbreaking of the facility in October 2018.

A Certificate of Completion issued on February 14, 2020, stated that the project had been fully completed as of January 9 of that year.

However, COA said the complex remained idle and unused since its reported completion, contrary to the requirement that government resources be protected against loss or wastage and used efficiently.

During an ocular inspection on August 7, 2025, auditors found the facility in a dilapidated state, with damaged portions of the building requiring repairs.

Although a security guard was assigned to the premises, the complex was being used mainly as a storage area for construction materials intended for other infrastructure projects.

Typhoon damages

The Provincial Engineering Office told auditors that the facility was completed before Typhoon Odette struck, with the storm allegedly damaging portions of the structure.

However, the office acknowledged that no comprehensive assessment had been conducted to determine the extent of the damage and the rehabilitation work needed.

COA also noted that the project remained recorded under Construction in Progress (CIP), even after the issuance of its completion certificate.

The Provincial Accountant explained that the final payment had not been processed because the contractor had not submitted a payment request.

Auditors said the prolonged failure to put the facility into operation deprived its intended beneficiaries of the public service for which it was built and could lead to additional government spending for repairs.

COA recommended that provincial officials explain why the project was reported completed despite its deteriorated condition, submit the completion documents, and assess whether the facility could still be repaired and rehabilitated.

The audit team also called for a definitive plan to restore the complex to a safe and functional condition.

Beyond the planned opening of the existing complex, Baricuatro said the province was also studying the construction of a bigger sports facility modeled after major sports complexes in Luzon.

“We plan to build a bigger one like the one in Clark (Pampanga). But atong gitan-aw karon ang location,” she said.

The governor said northern Cebu had previously been considered as a possible site for the proposed development as her administration works to position the province as a sports tourism destination.

Baricuatro added that the Philippine Sports Commission had expressed interest in extending an initial allocation of P1 billion for the proposed facility.

“The Philippine Sports Commission wants to allocate funds for us, so we're really looking into that,” she said.

Meanwhile, Capitol officials said the existing Lahug complex is expected to feature basketball and pickleball courts, along with a training hall for athletes.

The provincial government is also considering the Philippine Sports Commission's earlier interest in using the facility as a regional gymnastics training center. — /IHM (FREEMAN)

CEBU PROVINCIAL

  • Latest
Latest
Latest
abtest
Recommended
Are you sure you want to log out?
X
Login

Philstar.com is one of the most vibrant, opinionated, discerning communities of readers on cyberspace. With your meaningful insights, help shape the stories that can shape the country. Sign up now!

Get Updated:

Signup for the News Round now

FORGOT PASSWORD?
SIGN IN
or sign in with