Despite mayor’s December target: CCMC far from completion

Caecent No-ot Magsumbol - The Freeman

CEBU, Philippines — With just over a month before Mayor Nestor Archival’s self-imposed December target to complete the Cebu City Medical Center (CCMC), the long-delayed hospital construction remains far from finished, despite significant progress on its upper floors and extensive reconstruction still needed on the first three levels.

Kenneth Siasar, Archival’s chief of staff and newly appointed assistant city administrator, said that work on the hospital’s fourth, fifth and sixth floors has advanced considerably since the current contractor resumed construction.

“Misuroy na ko sa CCMC sa fourth floor, sa fifth floor ug sixth floor. In terms of cubicles, in terms of rooms, okay na siya. Nagsugod na sila og butang sa uban pang mga kinahanglanon nga tiwasonon,” Siasar said.

He said areas that were previously bare and largely vacant now have facilities for patients and hospital personnel.

“Pagpangadto ninyo(a few months back), bare kaayo tong area, bakante kaayo to tanan. Inig-sulod na ninyo karon, halos three floors kompleto na sa mga cubicles for the ICU and for the wards and other offices,” he said.

Siasar said major engineering and technical concerns have also been addressed, with Dakay Construction and Development Corp. undertaking mechanical, electrical, plumbing and fire protection works while adopting alternative construction methods to address issues previously flagged by the Commission on Audit (COA).

“Aduna'y laing pamaagi ang Dakay Construction aron ma-pursue nato ang construction in terms of mechanical, in terms of electrical, in terms of plumbing, and in terms of fire,” he said.

The contractor is also correcting structural deficiencies identified during building assessments.

Siasar said several columns require retrofitting, while unfinished beam connections, particularly near the operating room, are being completed.

“Naay mga haligi nga kinahanglan i-retrofit. Unya naa'y mga haligi nga wala matiwas ang connection, labi na'g inigsulod nimo sa CCMC going to OR…So gitiwas sa atong Dakay Construction. Mao nang inig-adto nato, connected na siya,” he said.

He stressed that despite the need for retrofitting, the existing structure remains stable.

“Although lig-on gihapon tungod kay miagi bitaw'g intensity six wa man maunsa. But wala lang sila(previous contractor) mu-follow sa design. Mao na'y gi-comply karon,” Siasar said.

Despite the progress on the upper floors, he acknowledged that substantial work remains, particularly on the first three levels.

Once the wards and intensive care unit facilities on the fourth to sixth floors are ready for use, patients occupying the lower floors will be transferred upstairs to allow reconstruction to proceed.

“Ang atoa lang is, the moment nga mahuman na nang four, five, six, ang kining pasyente nato sa first, second, third isaka nato,” he said.

“Unya ato na sang trabahuon ang first, second ug third floor. Tanan.”

Siasar explained that many facilities on the lower floors were only temporary arrangements put in place when portions of the hospital were opened to serve patients while construction continued.

“Temporary pa man nang atong first, second ug third floor,” he said.

“In fact kanang atong outpatient department, kung makita ninyo naay mga cubicle, that's not intended for patients, that's intended for commercial. Gigamit lang nato for the meantime sa outpatient department.”

He noted that CCMC has continued serving the public despite the unfinished construction.

“Actually, for the last two or three years, operational naman nang CCMC,” he said.

Siasar, who also serves as CCMC administrator, clarified that the current construction contract was awarded before Archival assumed office.

Dakay Construction received its notice of award in March 2025 and notice to proceed in June 2025, before Archival took office on July 1.

“So when the mayor assumed office July 1, existing na ang contractor sa CCMC,” Siasar said.

He said Archival first ordered a comprehensive assessment of the entire building before allowing the contractor to proceed.

“So what did the mayor do is gipa-evaluate lang sa niya the entire building before allowing the new contractor to commence base sa ilang kontrata,” Siasar said.

The CCMC reconstruction is among Cebu City’s longest-delayed infrastructure projects.

The original hospital building was deemed unsafe following the magnitude 7.2 earthquake that struck Bohol in October 2013. It was eventually demolished, with reconstruction beginning in 2015.

The project has since suffered repeated delays, contract issues and funding problems.

In June 2025, the previous administration awarded Dakay Construction a P700-million contract covering portions of the hospital’s third to seventh floors, with a completion period of 240 calendar days.

Archival, who repeatedly vowed during his campaign to finish the hospital, ordered a review of the project upon assuming office and sought greater transparency on the scope of work and funding requirements.

State auditors have also flagged engineering document deficiencies, implementation delays and other issues affecting various phases of construction.

Siasar said a walkthrough of the upper floors is being planned once the ongoing work reaches a more presentable stage, allowing the public to see the progress and remaining work on the long-delayed hospital. — (FREEMAN)

TRENDING

  • Latest
Latest
Latest
abtest
Are you sure you want to log out?
X
Login

Philstar.com is one of the most vibrant, opinionated, discerning communities of readers on cyberspace. With your meaningful insights, help shape the stories that can shape the country. Sign up now!

Get Updated:

Signup for the News Round now

FORGOT PASSWORD?
SIGN IN
or sign in with