Cebu power gap threatens to slow economic growth
CEBU, Philippines — Cebu’s accelerating economic growth is exposing a widening weakness in the Visayas power system, with recurring supply alerts highlighting the risk that electricity shortages could constrain business expansion, deter investment and undermine the region’s ability to sustain new economic activity.
The return of two generating units operated by Therma Visayas Inc. (TVI) in Toledo City has restored 338 megawatts (MW) to the grid, easing immediate supply pressures. But the improvement has done little to address the region’s underlying dependence on power imports and its limited buffer against generating plant outages.
Yellow and red alerts in October, followed by another yellow alert on Nov. 4, show the fragility of electricity supply in an economy where demand is expanding rapidly.
For businesses, the recurring alerts raise concerns over the reliability of power needed to sustain manufacturing, commercial operations and infrastructure development.
Department of Energy (DOE) Secretary Sharon Garin warned that the Visayas has gone too long without sufficient additions to baseload generation, leaving the grid exposed to disruptions whenever a major power plant goes offline.
“Even with the absence of just a single power plant, we will go on alert and that is not good for business,” she told lawmakers during an Oct. 3 congressional hearing in Bacolod City.
The risk is most pronounced in Cebu, the region’s largest electricity market, where demand is approaching 1,300 MW against local generating capacity of about 900 MW. The resulting shortfall forces the island to rely on electricity transfers from other parts of the Visayas and imports from Luzon and Mindanao.
That dependence leaves businesses exposed to transmission bottlenecks and supply disruptions beyond the province’s control. The Luzon-Visayas interconnection, despite having a nominal transfer capacity of about 440 MW, has at times carried only around 250 MW as grid operators maintain contingency reserves and voltage stability.
The supply constraints could become a more significant obstacle as Cebu attracts new investments and businesses seek to expand operations. Without sufficient and dependable electricity, power availability risks becoming a limiting factor for projects requiring substantial and uninterrupted energy supply.
Cebu’s electricity demand is growing by about 14 percent annually, more than twice the national average of roughly 6 percent. The province accounts for approximately 42 percent of total electricity demand in the Visayas, making its power requirements central to the region’s economic outlook.
“Cebu is the fastest growing. We don’t want Cebu’s economy to slow down because of electricity challenges,” Garin said.
Addressing the supply gap will require investments in both local generation and transmission infrastructure. The planned Cebu-Leyte Interconnection Lines 3 and 4 are designed to add 1,200 MW of transfer capacity, improving the movement of electricity across the region and reducing transmission constraints.
Battery energy storage systems, distributed solar installations and demand-side management could provide additional flexibility in the near term, helping stabilize the grid while larger generating facilities are developed.
The Energy Regulatory Commission (ERC) has granted provisional authority for East Asia Utilities Corp.’s 44.72-MW battery energy storage system in Mactan to provide up to 13 MW each of firm regulating and contingency reserves.
Longer-term additions include two coal-fired projects in Cebu with a combined planned capacity of 257 MW. TVI is targeting commercial operations in 2028 for its 150-MW expansion in Toledo, while Cebu Energy Development Corp.’s 107-MW project is expected in 2029.
Garin said projects qualifying under existing exemptions to the government’s coal moratorium may proceed, particularly expansions at established power plant sites.
The timing of these investments will be important for businesses weighing expansion plans against the region’s electricity constraints. The planned generation projects are not expected to come online until 2028 and 2029, leaving the grid reliant on existing capacity, imports and interim solutions in the meantime.
The return of TVI’s generating units has provided some breathing room, but it has not eliminated the structural supply gap. With electricity demand rising faster than the development of new capacity, Cebu faces the prospect of increasingly tight power conditions unless generation and transmission investments keep pace.
For investors, the issue extends beyond the risk of occasional power alerts. Reliable electricity is a prerequisite for industrial expansion, commercial development and the competitiveness of the province as an investment destination. Unless the power system can deliver sufficient capacity at the scale and reliability businesses require, Cebu’s energy constraints could become an increasingly costly brake on its economic growth.