NSCR Valenzuela-Malolos segment operational by 2028

Transportation Secretary Vince Dizon inspects the North-South Commuter Railway’s Malanday depot in Valenzuela City on November 18, 2026.

MANILA, Philippines — The North-South Commuter Railway (NSCR)’s Malolos-Valenzuela segment is scheduled to be operational by the first quarter of 2028, Transportation Secretary Vince Dizon announced yesterday.

Dizon made the statement during inspection of the NSCR Malanday depot in Valenzuela City, with the segment having four eight-car trainsets and more expected to arrive in February 2027.

The segment will feature seven stations and is expected to cut travel time from 60 to 30 minutes.

“This will be the start of the first operational line segment of the NSCR. We are almost 90 percent finished here at the depot, including the stations. By the end of the year, we will be at 95 percent for the connection of the train station all the way from Valenzuela to Malolos,” Dizon said.

Dizon earlier said the Clark segment of the NSCR is expected to be operational by 2029 and will shorten travel time from Makati to Clark International Airport from almost two hours to less than one hour.

“It will exceed a little more than the President’s term, but what’s important is that the Makati to Clark segment will be finished by 2029,” he said.

The 147-kilometer rail project will connect Metro Manila to Pampanga and Laguna.